V2 The Installation of a Roof Mounted Solar PV System, Replacement of Lighting, Heating and Hot Wate...
Main contract details
i. Replacement of the existing gas fired boiler plant with new packaged external air source heat pumps, new primary and secondary distribution pumps, new plant room pipework and associated systems.
ii. New controls system for the new heating.
iii. Replacement of heat emitters throughout the building.
iv. Construction of external plant enclosure (concrete base and fence) for the new air source heat pump units.
v. Replace fluorescent lighting with LED.
vi. Installation of a roof mounted solar PV system.
at Wick Primary School, Church Road, Wick, South Gloucestershire, BS30 5PD.
This work is being undertaken as part of the Council’s 2023/24 Schools Capital Repair and Maintenance Programme. Partial funding for the project has also been received from the Public Sector Decarbonisation Fund Phase 3b.
The Council is seeking a Gas SafeTM/ NICEIC Approved Electrical Contractor to act as Principal Contractor with the capability and experience to manage specialist sub-contractors to undertake and execute the contract works. The Council will not consent to the whole of the works to be sub-contracted. It is essential that this project is successfully executed during the summer recess, so the Contractor will need to demonstrate they have recently completed at least one similar project successfully (similar scope of work, similar value and similar timescale) and they have the competency and sufficient resources to meet these deadlines.
The Contractor shall appoint a full-time site-based representative (i.e. site/contract manager) throughout the works on site. It is expected the contractor will have to work longer weekdays and weekends during the school holiday period (24th July to 31st August 2023) to complete the work within the contract programme requirements and include these costs in their tender.
The works shall be carried out in accordance with the Construction (Design and Management) Regulations 2015. The Contractors will need to demonstrate they are fully conversant with their responsibilities under the Regulations in their tender return and allow for all costs associated with their management of the Contract.
The whole of the works are to be carried out in accordance with the terms and conditions of the JCT Standard Building Contract without Quantities 2016, published on behalf of The Joint Contracts Tribunal Limited by Thomson Reuters (Legal) Limited trading as Sweet & Maxwell. The Contractor shall obtain a copy of The Joint Contracts Tribunal Limited Standard Building Contract without Quantities 2016 and shall make themselves aware of the conditions therein. The solar PV system will be a contractors designed portion (CDP) under the JCT contract.
The deadline for tender returns is 26th June 2023 at 5pm.
Key dates
Expression of interest window
From 01/06/2023 10:00 to 26/06/2023 17:00
New to ProContract?
If you are not currently registered on the ProContract procurement portal, you can complete a simple registration process by clicking the following link - Register free
Contact details
Yate
Avon
BS37 5AF
United Kingdom