Project Description:
It is anticipated that the following works shall be discharged as part of these works:
a) Removal by abrasion of the existing structural/ texturized track surface and runways.
b) Power washing and brushing of the existing surface.
c) Complete removal and offsite disposal of the existing polymetric surface on lane 1
d) Full reconstruction of the polymetric surface on lane 1 which shall be suitably level
with the surrounding track
e) Install a non-porous polymeric structural/ textured layer track surface to all polymeric
track areas, runways and disabled access.
f) Supply / installation specialist ‘rubber top’ kerbing to UKA/IAAF requirements for long
jump beds.
g) Augment the existing steeple chase pit to comply with UKA/ IAAF requirements for
continuous polymeric surfacing over the pit edges.
h) Remedial works to the D areas to remove standing water by fixing levels to achieve
a constant fall to the drainage network.
i) Replace/ reset broken precast concrete flags surrounding the track.
j) Set out, survey and line mark in 2 part polyurethane paint all events to UKA/IAAF
requirements:
k) Obtain UKA certificate inclusive of dimensional survey:
l) Performance testing to IAAF requirements including certification;
m) Make good damaged landscape areas as a result of the work.
Full details relating to the Works are provided in the tender documents.
Contract Period:
The contract will be for a period of 1 month commencing 12th September 2016.
The relevant tender documents are included within this project webpage as attachments.
Questionnaire/ Tender Responses are required to be submitted no later than 15th July 2016, 14.00GMT by hardcopy to David James only.
If you require any clarifications on the tender documents please submit these in writing via e-mail, including the project name clearly in the e-mail title, to David James at djames@swindon.gov.uk by 7th July 2015, 12.00 GMT.
The Council’s responses to these clarification questions will be uploaded as attachments on the project webpage attachments section. Therefore it is the Contractor’s responsibility to check the site regularly for updates to clarifications, as you will not be advised when updates have been made.
In the event of difficulties downloading tender documents, please refer to the named contact David James at djames@swindon.gov.uk.
Please note that this project has been advertised on Contracts Finder/ other web portals, however, Supplying the South West Portal is the only portal that includes all the relevant documents required to respond to this opportunity, bearing Project Id: DN169115
We would encourage you to click on the ‘Register interest’ button to help the Council monitor the level of interest in this opportunity.
No Tender submissions will be considered without completing the tender documents in full including attachments and returning them in alignment with the instructions within the tender documents.
Key dates
Expression of interest window
From 27/06/2016 10:12 to 11/07/2016 10:12
New to ProContract?
If you are not currently registered on the ProContract procurement portal, you can complete a simple registration process by clicking the following link - Register free
Contact details
Swindon
Wiltshire
SN1 2JH
United Kingdom