MER- Hot Water & Heating Improvements
Main contract details
The project involves the upgrade and improvement heating and domestic hot water infrastructure, including the replacement and installation of heating pumps, modifications to existing heating circuits, Heat Interface Unit (HIU) adaptations, installation of point-of-use water heaters, Building Management System and controls integration, associated electrical works, commissioning, testing and related builders' works.
The works will be delivered in accordance with a completed design and specification prepared by the Trust's independent consultant. Design information will be available at the Supplier Questionnaire stage.
The Trust is inviting suppliers to register their interest in this opportunity. Following the close of the interest window, interested suppliers will be invited to complete a Supplier Questionnaire, which will be used to assess suppliers' suitability and capability to undertake the works. The Supplier Questionnaire will form the basis of the shortlisting process and only shortlisted suppliers will be invited to participate in the Invitation to Tender stage.
The Supplier Questionnaire will assess:
-Relevant experience of delivering heating, hot water and M&E improvement projects.
-Technical competence and organisational capability.
-Financial standing, Modern Slavery and GDPR.
-Health and Safety arrangements and accreditations.
-Availability and resources to deliver the project within the required programme.
-Ability to undertake the works in accordance with the completed design, specification, drawings and schedules issued by the Trust.
-Confirmation that all personnel attending site will hold, or be capable of obtaining, Enhanced DBS clearance where required.
Suppliers will be required to confirm their ability to deliver the works during the following key access periods, which coincide with school holiday closures:
Phase 1 (Easter Holiday): 30 March 2027 to 9 April 2027
Phase 2 (May Half-Term Holiday): 31 May 2027 to 7 June 2027
Phase 3 (Summer Holiday Completion Period): 26 July 2027 to 31 August 2027
The Trust expects the majority of disruptive works to be undertaken during these periods in order to minimise disruption to teaching and learning activities.
Indicative Procurement Timetable
Interest Window Opens 16 November 2026
Interest Window Closes 30 November 2026
Supplier Questionnaire Issued 02 December 2026
Supplier Questionnaire Return Deadline14 December 2026
Shortlisting of Suppliers15 December 2026
Invitation to Tender Issued 17 December 2026
Tender Return18 January 2027
Contract Commencement 25 March 2027
The above dates are an indicative timeline and maybe subject to change at the Trust's discretion.
The estimated contract value is currently anticipated to be in the region of £250,000 excluding VAT. This figure is indicative only and may be subject to change.
Interested suppliers should register their interest via the Trust's e-tendering portal Proactis. https://procontract.due-north.com/
Participation in this interest window does not guarantee invitation to tender and no evaluation or selection will take place at this stage. Shortlisting will be based solely on the assessment of the Supplier Questionnaire responses and compliance with the Conditions of Participation published as part of the formal procurement process.
This notice is issued for preliminary market engagement and market awareness purposes only and does not constitute a call for competition, Invitation to Tender, or commitment by the Trust to commence a procurement process
Key dates
Expression of interest window
From 16/11/2026 10:30 to 30/11/2026 12:00
New to ProContract?
If you are not currently registered on the ProContract procurement portal, you can complete a simple registration process by clicking the following link - Register free
Contact details
Earley
Berkshire
RG6 7HS
United Kingdom