Southern Connector Road
Main contract details
The proposed scheme will consist of the following key components:
• Part signalisation of the A419 Commonhead Roundabout;
• Improvement to existing Pack Hill, leading to the proposed SCR roundabout;
• New roundabout at the junction of the SCR and Pack Hill;
• New T-Junction and realignment of The Marsh;
• New bridge over Liden Brook and two culverts to accommodate local minor live streams;
• New signalised crossroads at the junction with Wanborough Road; and;
• Tie-in with the NEV development based on the 2016 Masterplan
The contract term will be 86 weeks as stated in the ITT documents. Estimated contract spend is £18,437,520
Full details relating to the Works are provided in the tender documents.
To participate in this Restricted Procedure, Suppliers will need to Register as a Supplier with ProContract, www.supplyingthesouthwest.org.uk, then Register an Interest before obtaining access to the Selection Questionnaire (SQ) and draft tender documents. In the event of difficulties registering as a supplier, please refer to the System Administrator Proactis support team ProContractSuppliers@proactis.com
SQ clarifications to be submitted in writing via Messaging in ProContract tender portal, including the project reference and title clearly in the Subject title, by 10th August 2020, 1400 hrs UK Local time. The Council’s responses to these clarification questions will be issued periodically via Messaging in ProContract tender portal.
SQ responses are required to be submitted no later than 17th August 2020, 1400 hrs UK Local time via ProContract tender portal - https://www.supplyingthesouthwest.org.uk/
Estimated date of dispatch of invitations to tender or to participate to selected candidates Date: 24/08/2020
Please note that this project has been advertised on Tenders Electronic Daily (TED) Contract Notice temporary reference 20-354548-001 Contracts Finder/ other web portals, however, Supplying the South West Portal, https://www.supplyingthesouthwest.org.uk/ is the only portal that includes all the relevant documents required to respond to this opportunity, bearing Project Id: DN487900
No submission will be considered without completing the SQ documents in full including attachments and returning them in alignment with the instructions within the SQ.
Key dates
Expression of interest window
From 17/07/2020 12:00 to 17/08/2020 14:00